Minister of Transport and Infrastructure Abdulkadir Uraloğlu announced that work is continuing on the Halkalı-Ispartakule and Ispartakule-Çerkezköy sections of the Halkalı-Kapıkule High-Speed Train Line. It was stated that with the 76-kilometer section, which will also operate as a suburban line like an extension of Marmaray, approximately 3.1 million people around Esenyurt, Bahçeşehir and Ispartakule will be connected to the rail system network.
The Edirne section of the Halkalı-Kapıkule High-Speed Railway Line entered service in October. Construction work continues on the remaining sections of the line that will connect Istanbul to Thrace.
TWO SECTIONS TOTALING 76 KILOMETERS
According to information provided by Minister Uraloğlu, a line suitable for speeds of 200 kilometers per hour and totaling 76 kilometers in length is being built in the Halkalı-Ispartakule and Ispartakule-Çerkezköy sections. The 153-kilometer Çerkezköy-Kapıkule section of the Halkalı-Kapıkule line was opened for service by President Recep Tayyip Erdoğan on October 9.
TUNNEL WORKS IN HALKALI-ISPARTAKULE
The approximately 9-kilometer Halkalı-Ispartakule section includes an approximately 6.4-kilometer TBM tunnel, open track, cut-and-cover structures, and connecting tunnels. The permanent lining works for the connecting tunnels have been completed. Tunnel, superstructure, and electromechanical works are ongoing.
3 STATIONS IN ISPARTAKULE-ÇERKEZKÖY
The approximately 67-kilometer Ispartakule-Çerkezköy section is being built as double-track, electrified, and signaled. The section, where passenger and freight transport will be carried out together, will include 3 stations and 6 passenger platforms. The project also plans 9 bridges, 6 viaducts, and 18 ecological underpasses and overpasses. Excavation work continues in the TBM tunnels, which have a total length of 12,210 meters.
WILL OPERATE AS AN EXTENSION OF MARMARAY
Uraloğlu stated that the line will not only be a high-speed railway line but will also operate as a commuter line, like an extension of Marmaray after Halkalı. According to the Ministry, this will connect approximately 3.1 million people living around Esenyurt, Bahçeşehir, and Ispartakule to the Marmaray network. Passengers in this area will be able to reach most of Istanbul from Marmaray stations extending to Gebze.
4-HOUR JOURNEY TO DROP TO 1.5 HOURS
With the completion of the line, annual passenger capacity is expected to increase from 600,000 to 3.4 million, and freight transport capacity from 1.5 million tons to 9.6 million tons. The passenger travel time between Halkalı and Kapıkule is targeted to decrease from 4 hours to 1.5 hours, and freight transport time from 8.5 hours to 3.5 hours.
EUROPE CONNECTION WILL BE STRENGTHENED
Minister Uraloğlu said the project, together with the Baku-Tbilisi-Kars Railway Line and Marmaray, will strengthen the Middle Corridor's connection to Europe. The line is also located at the western end of the Development Road Project, which is planned to extend from Faw Port in the Persian Gulf through Iraq and Turkey to Europe.
TARGET DATES CHANGED
In November 2024, Minister Uraloğlu stated that 74 percent progress had been achieved in the Halkalı-Ispartakule section and announced that they aimed to complete the works by the end of 2025. This year, during Ramadan, Uraloğlu said that construction work in the section was planned to be completed by the end of the year and that test works would begin at the beginning of the year. According to the international railway publication Railway Journal, the Halkalı-Ispartakule section is expected to enter service in 2027, and the Ispartakule-Çerkezköy section in 2028.